FREE RESOURCES

Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Drainage

Common labour factors for drainage to guide task time duration expectations, including stormwater and more...
Constants include laying, jointing and testing, but exclude excavation and backfilling

Description
Man Hours
Unit

Sewer and Stormwater Drains




Earthenware pipe, with rubber ring joints, diameter




Sewer




  • 100mm

  • 0.50
    hrs/m
  • 150mm

  • 0.70
    hrs/m
  • 225mm

  • 1.00
    hrs/m

    Stormwater




  • 100mm

  • 0.02
    hrs/m
  • 150mm

  • 0.37
    hrs/m
  • 225mm

  • 0.50
    hrs/m

    Bends,Junctions




  • 100mm

  • 0.25
    hrs/No.
  • 150mm

  • 0.25
    hrs/No.
  • 225mm

  • 0.50
    hrs/No.

    PVC pipe, with solvent welded joints, diameter




    Sewer




  • 100mm

  • 0.25
    hrs/m
  • 150mm

  • 0.60
    hrs/m

    Stormwater




  • 100mm

  • 0.20
    hrs/m
  • 150mm

  • 0.35
    hrs/m

    Bends, junctions




  • 100mm

  • 0.25
    hrs/No.
  • 150mm

  • 0.30
    hrs/No.

    Concrete pipe,with rubber ring joints, diameter




  • 100mm

  • 0.35
    hrs/m
  • 150mm

  • 0.43
    hrs/m
  • 225mm

  • 0.50
    hrs/m
  • 300mm

  • 0.65
    hrs/m