Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Demolition - Structure

For a feasibility study, your Demolition breakdown is 25% labour, 0% material, and 75% fixed costs.

Description
Man Hours
Unit

Floors




Remove vinyl floor tiles or carpet


0.20
hrs/m2

Break up and remove concrete floor topping




  • 100mm thick

  • 1.00
    hrs/m2
  • 150mm thick

  • 1.50
    hrs/m2

    Scabble concrete to receive new screed


    0.20
    hrs/m2

    Walls




    100mm thick masonry wall


    0.40
    hrs/m2

    200mm thick masonry wall


    0.80
    hrs/m2

    Timber framed partly glazed plasterboard wall


    0.30
    hrs/m2

    Remove ceramic wall tiles on solid plaster, make good to receive paint finish


    1.00
    hrs/m2

    Cut and form opening in single skin masonry wall for single door, including toothing and bonding, and making good to render


    7.00
    hrs/item

    Roofing/Ceilings




    Take down suspended ceiling system


    0.30
    hrs/m2

    Remove asphalt roofing, make good


    1.00
    hrs/m2

    Windows and Doors




    Remove




  • 2400mm x 900mm steel window

  • 2.20
    hrs/item
  • 3200mm x 2700mm roller shutter door

  • 4.00
    hrs/item

    Remove door, including hardware, frame and architrave




  • Pair of solid core doors

  • 1.25
    hrs/item
  • Single hollow core door

  • 0.50
    hrs/item