Structural Steelwork

Common labour factors for Structural Steelwork.

For a feasibility study, your Structural Steel breakdown on site is 10% labour, 90% materials and 0% fixed costs.

← Back to Labour Factor Trade Directory
Structural Steelwork
Description
Man Hours
Unit

Framing and Bracing




These labour constants refer to traditional estimating methods.




Heavy sections, including connections—UB, UC, RSJ and RSC




  • Fabrication

  • 23.00
    tonne
  • Erection

  • 7.00
    tonne

    Light sections—angles etc.




  • Fabrication

  • 40.00
    tonne
  • Erection

  • 20.00
    tonne

    Hollow sections, including connections




  • Large sections, fabrication

  • 30.00
    tonne
  • Large sections, erection

  • 10.00
    tonne
  • Small sections, fabrication

  • 35.00
    tonne

    Small sections, erection


    15.00
    tonne

    Trusses, including connections




  • Up to 10m span, fabrication

  • 50.00
    tonne
  • Up to 10m span, erection

  • 10.00
    tonne
  • Over 10m span, fabrication

  • 35.00
    tonne
  • Over 10m span, erection

  • 6.00
    tonne

    Proprietary purlins and girts




  • Up to 150mm high

  • 0.09
    hrs/m
  • Over 150mm high

  • 0.12
    hrs/m

    Surface Treatment




    Sand blast and paint




  • Light sections

  • 8.00
    tonne
  • Heavy sections

  • 5.00
    tonne