Solid Plaster

Common labour factors for Solid Plaster.

For a feasibility study, your Solid Plaster breakdown is 80% labour, 20% materials and 0% fixed costs.

← Back to Labour Factor Trade Directory
Solid Plaster
Description
Man Hours
Unit

Hardwall Plaster - interior




16mm thick in 2 coats




  • Walls

  • 0.42
    hrs/m2
  • Soffits

  • 0.50
    hrs/m2
  • Columns

  • 0.55
    hrs/m2
  • Beams

  • 0.55
    hrs/m2
  • Skim Coats on Walls

  • 0.15
    hrs/m2
  • Skim Coat on Soffits/Ceiling

  • 0.22
    hrs/m2
  • Plaster Coving

  • 0.15
    hrs/m
  • Plaster nosing

  • 0.15
    hrs/m

    Cement Render - exterior




    16mm thick in 2 coats




  • Walls

  • 0.30
    hrs/m2
  • Soffits

  • 0.32
    hrs/m2
  • Columns

  • 0.42
    hrs/m2
  • Beams

  • 0.42
    hrs/m2