FREE RESOURCES

Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

For a feasibility study, your Insitu Concrete breakdown is 15% labour, 80% materials and 5% fixed costs,
and your Formwork breakdown is 80% labour, 20% materials and 0% fixed costs.

Description
Man Hours
Unit

Constants assume five uses of formwork.
Where the number of uses is less, the constants should be adjusted by the percentage shown:




  • Four uses
  • Add +2.5%


  • Three uses
  • Add +6.0%


  • Two uses
  • Add +12.5%


  • One use
  • Add +20.0%


    Rates include fabrication, fixing in place and striking.




    Formwork to sides of

    Surface Finish


    Column/pier foundations

    F1
    1.20
    hrs/m2

    Strip footing

    F1
    1.20
    hrs/m2

    Attached beam

    F4
    2.45
    hrs/m2

    Column

    F4
    2.90
    hrs/m2
    F1
    2.65
    hrs/m2

    Lintels and beams

    F4
    3.50
    hrs/m2
    F4
    3.25
    hrs/m2

    Wall

    F4
    2.60
    hrs/m2
    F1
    2.20
    hrs/m2

    Formwork to soffit of




    Suspended slab

    F4
    2.35
    hrs/m2
    F1
    2.00
    hrs/m2

    Stairs and landings

    F4
    4.00
    hrs/m2
    F1
    3.50
    hrs/m2

    Formwork to edges, vertical or horizontal




    0–100mm high

    F4
    0.75
    hrs/m

    100–200mm high

    F4
    0.75
    hrs/m

    200–300mm high

    F4
    1.00
    hrs/m

    Form groove




    25mm x 25mm


    0.17
    hrs/m

    Form rebate




    100mm x 50mm


    0.27
    hrs/m

    Form hole/opening in concrete 100/200mm thick, size:




    100mm x 100mm


    0.32
    hrs/item

    300mm x 300mm


    0.54
    hrs/item

    500mm x 500mm


    0.80
    hrs/item

    Form hole/opening in concrete 200/300mm thick, size:




    100mm x 100mm


    0.40
    hrs/item

    300mm x 300mm


    0.67
    hrs/item

    500mm x 500mm


    0.87
    hrs/item

    Tube formers, cardboard, including stripping




    300mm ID (internal diameter)


    1.27
    hrs/m

    500mm ID


    1.53
    hrs/m

    Spirally wound plastic tube, including stripping




    300mm ID


    1.34
    hrs/m

    500mm ID


    1.60
    hrs/m

    For a feasibility study, your Insitu Concrete breakdown is 15% labour, 80% materials and 5% fixed costs,
    and your Formwork breakdown is 80% labour, 20% materials and 0% fixed costs.

    Description
    Man Hours
    Unit

    unreinforced readymix, placed in




    Blinding layer 50mm thick


    2.20
    hrs/m3

    Column and pier foundations


    1.20
    hrs/m3

    Strip footings


    1.30
    hrs/m3
  • Continuous concrete footings

  • 2.50
    hrs/m3
  • Small section continuous concrete footings under 300mm x 150mm or short sections of footings

  • 5.00
    hrs/m3

    reinforced readymix, placed in




    Column and pier foundations


    1.50
    hrs/m3

    Strip footings


    1.60
    hrs/m3

    Slabs and thickenings on fill


    1.75
    hrs/m3

    Suspended slabs 150/300mm thick


    2.00
    hrs/m3

    Walls 150/300mm thick


    2.00
    hrs/m3

    Columns


    2.90
    hrs/m3

    Attached beams


    2.25
    hrs/m3

    Isolated beams


    3.00
    hrs/m3

    Stairs and landings


    3.90
    hrs/m3

    Surface Finishes




    Hand Trowel


    0.15
    hrs/m2

    Power Float


    0.18
    hrs/m2

    Broomed Finish


    0.12
    hrs/m2

    Joints




    Keyed construction joint in




    150mm slab


    0.30
    hrs/m

    300mm slab


    0.35
    hrs/m

    Expansion joint in




    300mm slab


    0.60
    hrs/m

    150mm slab


    0.50
    hrs/m

    100mm and 125mm thick foundation walls


    5.00
    hrs/m3

    150mm wall


    0.60
    hrs/m

    150mm thick foundation walls


    4.50
    hrs/m3

    200mm thick foundation walls


    4.00
    hrs/m3

    300mm wall


    0.70
    hrs/m

    Attached piers to walls


    5.00
    hrs/m3

    Isolated piers and piles


    8.00
    hrs/m3

    Waterstops




    Waterstop, double bulb, cast in, excluding angles and intersections




    150mm wide


    0.25
    hrs/m

    200mm wide


    0.28
    hrs/m

    Concrete (Hand)




  • Large isolated pads

  • 2.50
    hrs/m3
  • Small isolated pads under 450mm x 450mm

  • 4.00
    hrs/m3
  • 75mm and 100mm concrete slabs

  • 2.50
    hrs/m3
  • Floating off slabs

  • 0.18
    hrs/m2
  • Small areas of slab

  • 4.00
    hrs/m3
  • Steps and supporting dwarf walls

  • 5.00
    hrs/m3
  • Large concrete beams

  • 6.50
    hrs/m3
  • Small concrete beams under 300 x 300mm

  • 13.00
    hrs/m3
  • Concrete filling to 200 x 200mm blockwork bond beams

  • 49.00
    hrs/m3
  • Concrete filling to 400 x 200mm blockwork bond beams

  • 73.00
    hrs/m3
  • Concrete filling to 250 x 200mm blockwork bond beams

  • 53.00
    hrs/m3
  • Concrete filling to cores in 200mm blockwork (per 100 lin metres of core)

  • 55.00
    hrs/m3
  • 100 x 100mm and 75 x 75mm concrete nibs to porch slabs

  • 16.00
    hrs/m3
  • Boxing to footings and pads

  • 1.30
    hrs/m2
  • Boxing to 100mm and 125mm foundation walls

  • 1.60
    hrs/m2
  • Boxing to 150mm walls

  • 2.20
    hrs/m2
  • Boxing to 200mm walls

  • 2.70
    hrs/m2
  • Boxing to attached piers at walls

  • 3.30
    hrs/m2
  • Boxing to piles standard lenghts

  • 1.00
    hrs/m2
  • Boxing to piles irregular lenghts

  • 1.30
    hrs/m2
  • Boxing to tall piers and columns over 1 metre high

  • 1.60
    hrs/m2
  • Boxing to soffit of slabs less than 1 metre from ground

  • 2.20
    hrs/m2
  • Boxing to soffit of slab over 1 metre but under 1.5 metres from ground

  • 2.70
    hrs/m2
  • Boxing to soffit of slab over 1.5 metres from ground

  • 3.30
    hrs/m2
  • Boxing to edges of 75mm and 100mm slabs

  • 26.00
    hrs/100 lineal metres
  • Soffit of slabs in small areas

  • 4.95
    hrs/m2
  • Soffits of suspended steps as per rate for slabs

  • 1.95
    hrs/m2
  • Risers to steps

  • 33.00
    hrs/100 lineal metres
  • Edges of steps including profile cutting

  • 3.30
    hrs/m2
  • Soffits and sides of large concrete beams (supports up to 1 metre high)

  • 3.30
    hrs/m2
  • Soffits and sides of large concrete beams (support over 1 metre high)

  • 3.80
    hrs/m2
  • Sides only of large beams

  • 2.70
    hrs/m2
  • Soffits and sides of small beams

  • 2.70
    hrs/m2
  • Sides only small beams

  • 2.20
    hrs/m2
  • Raking beams - rate as per level beams

  • 3.38
    hrs/m2
  • Stop ends to walls sides of openings to walls

  • 40.00
    hrs/100 lineal metres
  • Soffits of openings in walls

  • 60.00
    hrs/100 lineal metres
  • Form openings for vents

  • 15.00
    hrs/100 No.
  • Build in holding down bolts

  • 6.00
    hrs/100 No.
  • Build in galv. wire ties

  • 3.00
    hrs/100 No.
  • Form large rebates and chases

  • 20.00
    hrs/100 lineal metres
  • form small rebates and chases planted fillets

  • 10.00
    hrs/100 lineal metres
    linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram