Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Soft Landscaping

Here you'll find hard and soft landscaping, from fencing to planting.

Description
Man Hours
Unit

Excavation - Tree Pits




0.8 x 0.8 x 1200mm deep tree pits for all Specimen grade trees


2.50
hrs/No.

0.5 x 0.5 x 560mm deep tree pits


1.50
hrs/No.

0.5 x 0.5 x 800mm deep tree pits


2.00
hrs/No.

0.45 x 0.45 x 700mm deep PB12 tree pits @ 2m centres


1.60
hrs/No.

Backfilling




0.8 x 0.8 x 800mm deep tree pits with specified mix for all Specimen grade trees


0.40
hrs/m3

0.5 x 0.5 x 400mm deep tree pits


0.33
hrs/m3

0.5 x 0.5 x 500mm deep tree pits


0.38
hrs/m3

0.45 x 0.45 x 400mm deep tree pits


0.33
hrs/m3

Lawn areas with 150mm clean topsoil


0.30
hrs/m2

Garden areas with 400mm clean topsoil.


0.30
hrs/m2

Tree Root Barriers




Tree Root Barriers to Specimen Trees


0.5
hrs/No.

Grassing




Lawn areas, including fertilizing and seeding, etc. at 50mm thick


0.25
hrs/m2

Specimen Tree Planting




Plant specimen trees in tree pits including fertiliser tablets.


3.5
hrs/No.

Stake specimen grade trees: 2 -
1600 x 50 x 50mm stakes per tree.


0.50
hrs/No.

Small Tree Planting




Set out and plant Hedge (PB12)


1.00
hrs/No.