Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Suspended Ceilings

For a feasibility study, your Suspended Ceilings breakdown is 20% labour, 80% materials and 0% fixed costs.

Description
Man Hours
Unit

Suspension Systems, suspended 600mm from concrete
soffit or steel purlins




Fully concealed suspension system


0.20
hrs/m2

Exposed grid system


0.18
hrs/m2

Linings




10mm plasterboard fixed to concealed suspension system


0.25
hrs/m2

Plasterboard tiles set into exposed grid system


0.14
hrs/m2