Drainage

Common labour factors for Drainage.

Common labour factors for drainage to guide task time duration expectations, including stormwater and more...
Constants include laying, jointing and testing, but exclude excavation and backfilling

← Back to Labour Factor Trade Directory
Drainage
Description
Man Hours
Unit

Sewer and Stormwater Drains




Earthenware pipe, with rubber ring joints, diameter




Sewer




  • 100mm

  • 0.50
    hrs/m
  • 150mm

  • 0.70
    hrs/m
  • 225mm

  • 1.00
    hrs/m

    Stormwater




  • 100mm

  • 0.02
    hrs/m
  • 150mm

  • 0.37
    hrs/m
  • 225mm

  • 0.50
    hrs/m

    Bends,Junctions




  • 100mm

  • 0.25
    hrs/No.
  • 150mm

  • 0.25
    hrs/No.
  • 225mm

  • 0.50
    hrs/No.

    PVC pipe, with solvent welded joints, diameter




    Sewer




  • 100mm

  • 0.25
    hrs/m
  • 150mm

  • 0.60
    hrs/m

    Stormwater




  • 100mm

  • 0.20
    hrs/m
  • 150mm

  • 0.35
    hrs/m

    Bends, junctions




  • 100mm

  • 0.25
    hrs/No.
  • 150mm

  • 0.30
    hrs/No.

    Concrete pipe,with rubber ring joints, diameter




  • 100mm

  • 0.35
    hrs/m
  • 150mm

  • 0.43
    hrs/m
  • 225mm

  • 0.50
    hrs/m
  • 300mm

  • 0.65
    hrs/m