For a feasibility study, your Insitu Concrete breakdown is 15% labour, 80% materials and 5% fixed costs,
and your Formwork breakdown is 80% labour, 20% materials and 0% fixed costs.
unreinforced readymix, placed in
Blinding layer 50mm thick
Column and pier foundations
Strip footings
reinforced readymix, placed in
Column and pier foundations
Strip footings
Slabs and thickenings on fill
Suspended slabs 150/300mm thick
Walls 150/300mm thick
Columns
Attached beams
Isolated beams
Stairs and landings
Surface Finishes
Hand Trowel
Power Float
Broomed Finish
Joints
Keyed construction joint in
150mm slab
300mm slab
Expansion joint in
300mm slab
150mm slab
100mm and 125mm thick foundation walls
150mm wall
150mm thick foundation walls
200mm thick foundation walls
300mm wall
Attached piers to walls
Isolated piers and piles
Waterstops
Waterstop, double bulb, cast in, excluding angles and intersections
150mm wide
200mm wide
Concrete (Hand)