Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

For a feasibility study, your Brickwork breakdown is 50% labour, 50% materials and 0% fixed costs.
and your Concrete Masonry breakdown is 25% labour, 75% materials and 0% fixed costs.

Description
Man Hours
Unit

Blockwork in walls, of hollow blocks




400mm x 200mm x 100mm


0.43
m2

400mm x 200mm x 150mm


0.5
m2

400mm x 200mm x 200mm


0.56
m2

400mm x 200mm x 200mm, hollow block threaded over reo bars


0.96
m2

Pointing and cleaning down


0.10
m2

Fair raking cutting




100mm hollow block


0.18
hrs/m

200mm hollow block


0.28
hrs/m

Concrete filling to cores of hollow blocks




150mm hollow block


0.45
hrs/m2

200mm hollow block


0.55
hrs/m2

Lintel block, including filling




200mm wide x 200mm high x 200mm long


0.40
hrs/m

200mm wide x 400mm high x 200mm long


0.54
hrs/m