Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Roof Framing

For small additions to buildings or for partitioning in commercial contracts, allow extra time to the give rate - up to 50% as required. Better to have more time than less.
For a feasibility study, your Carpentry breakdown is 45% labour, 55% materials and 0% fixed costs.

Description
Man Hours
Unit

Rafter




100mm x 50mm


0.18
hrs/m

150mm x 50mm


0.20
hrs/m

200mm x 50mm


0.22
hrs/m

Collar tie




150mm x 25mm


0.17
hrs/m

Strut and brace




100mm x 50mm


0.12
hrs/m

100mm x 75mm


0.22
hrs/m

Purlin/Roofing Batten




75mm x 50mm


0.12
hrs/m

100mm x 50mm


0.15
hrs/m

150mm x 50mm


0.17
hrs/m

200mm x 50mm


0.20
hrs/m

Eaves framing




75mm x 50mm


0.18
hrs/m

100mm x 50mm


0.20
hrs/m

Fascia




100mm x 50mm


0.17
hrs/m

150mm x 50mm


0.20
hrs/m

Ridge board




150mm x 25mm


0.20
hrs/m

200mm x 25mm


0.22
hrs/m

100mm x 50mm


0.17
hrs/m

Valley board




150mm x 25mm


0.18
hrs/m

200mm x 25mm


0.20
hrs/m

150mm x 50mm


0.16
hrs/m

200mm x 50mm


0.21
hrs/m

Purlin Beams and Lintels




200mm x 50mm


0.27
hrs/m

300mm x 75mm


0.34
hrs/m

200mm x 100mm


0.34
hrs/m

300mm x 100mm


0.45
hrs/m

Posts




100mm x 100mm


0.28
hrs/m

Prefabricated roof trusses, erection only




6m span


1.50
hrs/item

9m span


2.00
hrs/item

12m span


3.00
hrs/item