Labour Factor Database

Our comprehensive database makes it simple to search for and find the exact labour factors you need. The advanced filtering options let you narrow down your search based on your project needs, helping you plan and schedule your construction projects more effectively.
  • Search

  • Trade Categories

Wall Framing - Timber

For small additions to buildings or for partitioning in commercial contracts, allow extra time to the give rate - up to 50% as required. Better to have more time than less.
For a feasibility study, your Carpentry breakdown is 45% labour, 55% materials and 0% fixed costs.

Description
Man Hours
Unit

Plate




75mm x 50mm


0.12
hrs/m

100mm x 50mm


0.13
hrs/m

150mm x 50mm


0.15
hrs/m

Stud



hrs/m

75mm x 50mm


0.12
hrs/m

100mm x 50mm


0.13
hrs/m

150mm x 50mm


0.15
hrs/m

Jack stud




75mm x 50mm


0.13
hrs/m

100mm x 50mm


0.13
hrs/m

150mm x 50mm


0.24
hrs/m

Noggin/Dwangs




75mm x 50mm


0.13
hrs/m

100mm x 50mm


0.17
hrs/m

150mm x 50mm


0.24
hrs/m

Lintels




100mm x 100mm


0.26
hrs/m

150mm x 100mm


0.36
hrs/m

200mm x 100mm


0.46
hrs/m

250mm x 100mm


0.5
hrs/m

Bracing




Metal angle diagonal bracing


0.12
hrs/m

Plywood sheet bracing checked in flush


0.90
hrs/m2

Plywood sheet bracing fixed over framing


0.40
hrs/m2